Nearing completion of Phases 1 and 2

Construction of Phases 1 and 2 is nearing completion this month.  FPL has finally begun their power installation, with live power anticipated in Laguna Caribe by mid-August.  Final “punch list” items are being completed by the development team, and checked...

Construction update – May 5, 2022

Lots going on since our last update: FPL power distribution system installation continues, with the conduits and transformer pads to finish by mid-May, at which point installation of cabling and transformers by FPL comes next.  The delivery date for power to the...