Construction Update – March 15, 2023
L26 Development completed construction of the Phase 1 and Phase 2 infrastructure last week, certifying same to the County. Upon the County's verification, then our plat will be recorded and lot sales closings will commence thereafter. At this time our construction...
Construction Update – December 10, 2022
The biggest news is that FPL finally completed installation of the electrical power distribution system for Laguna Caribe earlier this month, which is now the trigger for certification of completion of our infrastructure construction by Lee County, which in turn...
Construction Update – September 15, 2022
Power finally arrives! The long awaited installation and delivery of electrical power to Laguna Caribe by FPL has finally happened in September, after months of delays. As anyone can imagine, electrical power is necessary to the operation of anything including...
Nearing completion of Phases 1 and 2
Construction of Phases 1 and 2 is nearing completion this month. FPL has finally begun their power installation, with live power anticipated in Laguna Caribe by mid-August. Final "punch list" items are being completed by the development team, and checked off for our...
Construction and Casita Update – June 21, 2022
Construction continues steadily since our last update in May:- We commenced construction of the club bath house- RV pad construction began, with grading, base rocking, and paving applied to the first 13 lots so far and continuing on through the summer until we...
Casita Update – May 18, 2022
Yesterday the Lee County Board of County Commissioners (BOCC) voted to amend the Land Development Code (LDC) to add casitas with indoor kitchens and bedrooms, of unlimited size, as allowable accessory use structures for Recreational Vehicle Planned Developments...
Construction update – May 5, 2022
Lots going on since our last update: FPL power distribution system installation continues, with the conduits and transformer pads to finish by mid-May, at which point installation of cabling and transformers by FPL comes next. The delivery date for power to the...
Construction Update – April 15, 2022
Our swimming pool and spa construction began this week, with the pool bathhouse construction also getting underway. Over the course of the next 3 months we'll complete construction of the tiki bar, pool and spa, pool deck with lighting and landscaping, bocce courts,...
Construction Update – March 29, 2022
We've gone vertical! The first of our several amenity facility buildings has just gone up - our Tiki Bar. The thatched/timber structure is now fully erected, while utilities, foundation, floor, lights, fans, and the bar itself will be installed in the next couple of...
Construction Update – March 15, 2022
While it's only been a few days since our last Construction Update post, we didn't want to wait. The Tiki Bar began construction yesterday, so this is the beginning our our amenities construction at Laguna Caribe. Just picturing in our minds, now, relaxing in the...