Power finally arrives! The long awaited installation and delivery of electrical power to Laguna Caribe by FPL has finally happened in September, after months of delays. As anyone can imagine, electrical power is necessary to the operation of anything including motorcoach lots and amenities.
With the arrival of power we can finally seek construction completion certification by Lee County and the State, which we now anticipate receiving within the next 30 days. With that accomplished we can record our plat, and commence the process of closing the purchases of lots already contracted, and more as time progresses. This will also enable us to set an opening date for rental of Developer owned lots this upcoming high season.
As for other construction activities, work on Phase 1 of the clubhouse including the Tiki Bar, bathhouse and pool complex continues, while foundation work continues on the Phase 2 clubhouse building. In the coming weeks the pool deck will be completed then the final interior finish of the pool. The construction of the pickleball courts began recently, with the bocce courts and golf putting green to also be installed with the completion of the pool deck paving. Landscaping of the common areas is now underway, and both paving and landscaping of the motorcoach lots continues with completion of all 137 lots anticipated by late fall.