We’ve gone vertical!
The first of our several amenity facility buildings has just gone up – our Tiki Bar. The thatched/timber structure is now fully erected, while utilities, foundation, floor, lights, fans, and the bar itself will be installed in the next couple of months. The underground utilities for the bathhouse and the mechanical room for the clubhouse are going in shortly, to be followed by foundations then the walls. The swimming pool and spa are finally permitted and construction will start very soon.
We’ve completed the underground utilities for both Phases 1 and 2, while paving of the Phase 2 half of Laguna Caribe Circle begins this week with installation of curbing. Construction of the RV pads and underground utility connections to the RV pedestals is underway now. Depending upon when Florida Power and Light completes their underground power distribution system, we anticipate obtaining a certificate of completion for Phase 1, and recording of the Phase 1 plat, in June. Phase 2 plat recording is anticipated to follow later this summer.