Construction Update – March 29, 2022

We’ve gone vertical! The first of our several amenity facility buildings has just gone up – our Tiki Bar. The thatched/timber structure is now fully erected, while utilities, foundation, floor, lights, fans, and the bar itself will be installed in the next...

Construction Update, March 10, 2022

We continue to make good progress on construction of Laguna Caribe since our last update a month ago. The underground utilities (water, sewer, and stormwater drain systems) for both Phases 1 and 2 are now substantially complete. FPL finally began installation of their...

Construction Update, February 10, 2022

Key construction milestones achieved this past month include the completion of the sanitary sewer system in both Phases 1 and 2, importation of most of the fill material required to create the final grades, and completion of road paving for Phase 1. The lakeshore was...

Construction Update, January 7, 2022

Happy New Year! Construction of Laguna Caribe continues apace.  The underground utilities for Phase 1 are now substantially completed with acceptance testing underway, and work will continue immediately on Phase 2 utilities.  Fill has continued to be imported to grade...

Construction Update, October 28, 2021

Since our last construction update in September, we have benefited from the beginning of our annual “dry season” here in southwest Florida. Dry weather in October significantly increases the pace of construction as we are no longer having to do much...