Construction update – May 5, 2022

Lots going on since our last update: FPL power distribution system installation continues, with the conduits and transformer pads to finish by mid-May, at which point installation of cabling and transformers by FPL comes next.  The delivery date for power to the...

Construction Update – April 15, 2022

Our swimming pool and spa construction began this week, with the pool bathhouse construction also getting underway.  Over the course of the next 3 months we’ll complete construction of the tiki bar, pool and spa, pool deck with lighting and landscaping, bocce...

Construction Update – March 29, 2022

We’ve gone vertical! The first of our several amenity facility buildings has just gone up – our Tiki Bar. The thatched/timber structure is now fully erected, while utilities, foundation, floor, lights, fans, and the bar itself will be installed in the next...

Construction Update, March 10, 2022

We continue to make good progress on construction of Laguna Caribe since our last update a month ago. The underground utilities (water, sewer, and stormwater drain systems) for both Phases 1 and 2 are now substantially complete. FPL finally began installation of their...

Construction Update, February 10, 2022

Key construction milestones achieved this past month include the completion of the sanitary sewer system in both Phases 1 and 2, importation of most of the fill material required to create the final grades, and completion of road paving for Phase 1. The lakeshore was...